Case-Study : 30Ton hot water project for hotel in Vietnam
发布时间:2025.04.23Case-Study : 30 tons Heat Pump hot water project
Here is the Case-Study about our 30 tons hot water project in our Vietnam customers :
Professional Budget Proposal for 30-Ton Heat Pump Hot Water System
Prepared for: [MiniMigo Hotel], Vietnam
Prepared by: [EVE ECO-PRODUCTS ]
Date: 2025-04-15
--
1. Project Overview
The proposed **30-ton heat pump hot water system** is designed to meet the daily hot water demands of your hotel with high energy efficiency and reliability. The system utilizes a **30P heat pump unit** paired with a **30-ton insulated water tank**, ensuring stable hot water supply while minimizing operational costs.
---
2. System Working Principle
The heat pump operates on the **reverse Carnot cycle**, transferring ambient heat energy to water through four stages:
- Evaporation: Ambient air is drawn into the evaporator, where refrigerant absorbs heat and vaporizes.
- Compression: The compressor pressurizes the vaporized refrigerant, raising its temperature.
- Condensation: High-temperature refrigerant releases heat to the water in the storage tank via a heat exchanger.
- Expansion: The refrigerant passes through an expansion valve, cooling and restarting the cycle.
**Key Advantages**:
- COP (Coefficient of Performance): 3.8–4.2 (1 unit of electricity generates 3.8–4.2 units of heat).
- Eco-friendly: Zero direct carbon emissions.
- 24/7 Operation: Stable performance in ambient temperatures of 10°C to 45°C.
---
3. System Components
---
4. Installation Process Flowchart**
Phase 1: Site Assessment
↓
Phase 2: Foundation Preparation (heat pump base + tank platform)
↓
Phase 3: Install Heat Pump Unit & Water Tank
↓
Phase 4: Connect Piping & Circulation System
↓
Phase 5: Electrical Wiring & Control System Setup
↓
Phase 6: System Testing & Commissioning
↓
Phase 7: Staff Training & Handover
---
4. Budget Estimate
Notes:
- Prices exclude optional backup power.
- Annual maintenance contract: ~$800/year (recommended).
---
6. Energy Savings & ROI
- **Annual Electricity Savings**: ~60% vs. electric boilers.
- **ROI Period**: 2–3 years (based on Vietnam’s electricity rates).
---
7. Conclusion
This system guarantees a **reliable, cost-effective hot water supply** for your hotel, aligning with Vietnam’s sustainability goals. We propose a project timeline of **6–8 weeks** from approval to commissioning.
For questions or adjustments, contact:
---
**Attachments**:
- Technical drawings
- Component certifications
- Warranty terms
**End of Proposal**
---
This template balances technical details and client-friendly explanations. Adjust costs and specs based on your company’s data. Let me know if you need further refinements!