Case-Study : 30Ton hot water project for hotel in Vietnam

发布时间:2025.04.23

Case-Study : 30 tons Heat Pump hot water project

Here is the Case-Study about our 30 tons hot water project in our Vietnam customers :

Professional Budget Proposal for 30-Ton Heat Pump Hot Water System

Prepared for: [MiniMigo Hotel], Vietnam

Prepared by: [EVE ECO-PRODUCTS ]

Date: 2025-04-15

--

1. Project Overview

The proposed **30-ton heat pump hot water system** is designed to meet the daily hot water demands of your hotel with high energy efficiency and reliability. The system utilizes a **30P heat pump unit** paired with a **30-ton insulated water tank**, ensuring stable hot water supply while minimizing operational costs.  

---

2. System Working Principle

The heat pump operates on the **reverse Carnot cycle**, transferring ambient heat energy to water through four stages:  

- Evaporation: Ambient air is drawn into the evaporator, where refrigerant absorbs heat and vaporizes.  

- Compression: The compressor pressurizes the vaporized refrigerant, raising its temperature.  

- Condensation: High-temperature refrigerant releases heat to the water in the storage tank via a heat exchanger.  

- Expansion: The refrigerant passes through an expansion valve, cooling and restarting the cycle.  

**Key Advantages**:  

- COP (Coefficient of Performance): 3.8–4.2 (1 unit of electricity generates 3.8–4.2 units of heat).  

- Eco-friendly: Zero direct carbon emissions.  

- 24/7 Operation: Stable performance in ambient temperatures of 10°C to 45°C.  

---

3. System Components

1745377248155092.png

---

4. Installation Process Flowchart**  

Phase 1: Site Assessment  

  ↓  

Phase 2: Foundation Preparation (heat pump base + tank platform)  

  ↓  

Phase 3: Install Heat Pump Unit & Water Tank  

  ↓  

Phase 4: Connect Piping & Circulation System  

  ↓  

Phase 5: Electrical Wiring & Control System Setup  

  ↓  

Phase 6: System Testing & Commissioning  

  ↓  

Phase 7: Staff Training & Handover  

---

4. Budget Estimate

1745377138708045.png

Notes:  

- Prices exclude optional backup power.  

- Annual maintenance contract: ~$800/year (recommended).  

---

6. Energy Savings & ROI

- **Annual Electricity Savings**: ~60% vs. electric boilers.  

- **ROI Period**: 2–3 years (based on Vietnam’s electricity rates).  

---

7. Conclusion

This system guarantees a **reliable, cost-effective hot water supply** for your hotel, aligning with Vietnam’s sustainability goals. We propose a project timeline of **6–8 weeks** from approval to commissioning. 

For questions or adjustments, contact:  

1745377038143755.png

---  

**Attachments**:  

- Technical drawings  

- Component certifications  

- Warranty terms  

 

**End of Proposal**  